Building on Faith 2008

We are currently gearing up from Building on Faith 2008.  We hope to have your support!

'Special Builds' Links

Women Build

Youth United Build

Thrivent Build

Global Village

Volunteer Opportunities

Building on Faith needs a lot of volunteer support.  For each of these days on the worksite we do not only need volunteers to help with construction.  We ask for your support in providing snack and lunch, leading devotions, and greeting volunteers on the worksite.  Before the build begins we also need support in fundraising and planning this event.  You are more than welcome to volunteer as a group or as an individual.

Registration Form

Click here to fill out an online volunteer registration form.
For downloadable PDF form, click here.

We appreciate your dedication to our mission to eliminate substandard housing. We hope your congregation, along with others, will take on this exciting task! Sharing in sponsoring a Tacoma/Pierce County Habitat for Humanity house is an amazingly rewarding experience that requires the involvement of people from all aspects of your congregation. As a sponsor, your role includes helping finance the house and providing volunteers to build the house in partnership with the family. It is a task that will be both challenging and rewarding, and most importantly, it is a task that will make a real and lasting positive impact on our community and Guatemala, where our tithe is used to build more affordable houses.

For more information, please contact:

Cassandra Jarles
Volunteer Services
253-627-5626, ext 19
E-mail Cassandra

Tue, 9/2

Framing, siding, porches, scaffolding

Wed, 9/3

Trusses, roof sheathing, felt & starter courses

Thu, 9/4

Roof shingles, exterior trim & caulking

Fri, 9/5

Siding, soffitts & rough plumbing/ electrical/mechanical

Sat, 9/6

Siding and soffitts

Mon, 9/8

Insulation

Tues, 9/9

Hang sheetrock

Wed, 9/10

Hang sheetrock

Thu, 9/11

Exterior trim & paint (contract drywall finish)

Fri, 9/12

Exterior trim & paint (contract drywall finish)

Sat, 9/13

Exterior trim & paint (contract drywall finish)

Mon, 9/15

Exterior trim & paint (contract drywall finish)

Tue, 9/16

Exterior trim & paint (contract drywall finish)

Wed, 9/17

Exterior trim & paint (contract drywall finish)

Thu, 9/18

Interior painting

Fri, 9/19

Cabinet install & electrical trim

Sat, 9/20

Closet/window trim, countertop install, base/casing trim, landscaping

Mon, 9/22

Hardware, plumbing trim, vinyl install

Tue, 9/23

Appliance install, inspections (plumbing, mechanical, electrical)

Wed, 9/24

Interior paint touch-up, fill holes, etc.

Thu, 9/25

Interior/exterior touch-up, landscape touch-up

Fri, 9/26

Carpet install, inspection (erosion control)

Sat, 9/27

Clean-up! Dedication! (Subject to change)